Detailed engineering of the Seville-Cádiz railroad line, Bajo de Cabezuela.

66 kV

High voltage power lines

Los servicios afectados por la nueva línea ferroviaria se analizaron y resolvieron de in agreement with the following organizations: Puerto Real City Council, supplier companies and other public bodies involved (the Guadalquivir Hydrographic Confederation, and DGT, General Directorate of Traffic).

Telephone and data transmission lines. Medium voltage power lines (20 kV) and High Voltage (66 kV) power lines. Street lighting design.

Natural gas supply, water supply, sewage and rainwater supply networks

 

Location Sevilla-Cádiz, Spain

Date: 2016-2017

Scope of the project: detailed engineering

Other projects

Power supply: HV/MV substation: 69/13.2 kV 14 MVA 3 MV/LV substations: 13.2 kV/480 V (400 kVA, 1,000 kVA and 3×2500 kVA) Complete MV design and

8 m Luminaire pole height Roundabout lighting design based on luminaires on 8 m high poles, lamps of

9 Piperack aerial hydrocarbon pipes: 9 hydrocarbon pipes: 5 x 14″, 4 x 18’ and pipes for other installations: 2 x 2″ of