3.342.759 €
Budget
Proes drafted the construction project for the seawater collection of the Mira fish farm in Portugal. It designed the connection piece for the intake line, consisting of a self-floating rectangular reinforced concrete box (16.8mx15.5mx8.15m) that connects three HDPE pipes (2×2000 mm+1×3000 mm) with a jacking pipe DN 3000 mm.
Among other activities, the hydraulic and structural calculations of the part are carried out, the naval stability is verified and the construction procedure is developed. During construction, Technical Consultancy is provided, developing, among other tasks, the monitoring system and the inspection and maintenance manual for the structure.
Location praia de Mira, Coimbra, Portugal
Date: 2012-2013
Presupuesto: 3.342.759 €
Scope of the project: constructive project and technical assistance