275.000 m3/day
producción de agua
400.000 m3/day
posibilidad de ampliación
This project includes the necessary works for seawater intake and brine discharge for the Agadir desalination plant in Morocco.
The construction of the desalination plant is planned in two stages. In the first phase, the necessary infrastructure will be provided to meet the production needs. In the second phase, the facilities will be expanded to supply double the flow. However, all the intake infrastructure is constructed for both phases.
Location Agadir, Morocco
Date: 2011
Scope of the project: diseño de las conducciones de captación y vertido de la desaladora, diseño de la torre de captación y cámara de bombas, estudio de dilución y de clima marítimo