60.000 m³
capacity
750.000
population
The purpose of the work is to draw up a construction project for a drinking water reservoir from the El Pardo junction and siphon.
Subsequently, in 2008, the construction project for the gallery inside which the outlet, inlet and relief pipes of the new reservoir will be connected to the respective pipes of the old one was drawn up. The gallery will be practicable and visitable at the levels corresponding to each pipe.
Location Majadahonda, Community of Madrid
Date: 2005-2008
Scope of the project: construction project for the construction of a drinking water reservoir and a gallery to connect to the existing reservoir.
Significant data: 60,000 m³ capacity for 750,000 inhabitants and maximum water level height of 7.80 m